Tax Impact Calculator

Town of Enfield | PreK to 5 + Eagle Academy Tax Impact Calculator
Town of Enfield

PreK to 5 + Eagle Academy Referendum

Projected Debt Service and Tax Impact by Fiscal Year — New Construction — $89 Million Town Share

Instructions

Start by using the following link to look up your property's appraisal value for fiscal year 2026-2027 (Oct 1, 2025 Grand List). Next, enter that information into the section below.

Look up your property in the Enfield Assessor's Database ↗

Enter the appraised value from the assessor's database (not the assessed value).

Assessed Value

Assessed Value (70% of appraisal)
$248,500
Calculated from the appraisal value entered above.

Your Estimated Tax Impact

Important: Please review the assumptions and explanation below. The following figures are estimates—not a prediction or guarantee of your future tax bill. Actual impacts may differ based on final borrowing costs, changes in the Town’s budget and tax base, property tax abatements and exemptions, and next year’s revaluation. The estimates do not account for every future change in municipal spending, revenues, or property values; your actual annual tax impact may be higher or lower than shown.

Calculations update automatically when you change the appraisal value.

Fiscal Year Estimated Annual Mill Rate Impact Estimated Annual Tax Impact
Total of estimated annual impacts shown $—
This is the sum of the estimated annual tax impacts for all listed fiscal years (2029–2057), assuming the same appraisal/assessed value throughout. It is an illustrative cumulative total—not a separate annual charge or a guarantee of what any taxpayer will pay over the life of the bonds.

Assumptions

  • Appraised Value is based on the 2025 Grand List (October 1, 2025 for the July 1, 2026 to June 30, 2027 fiscal year)
  • Cost of each building (provided by Tecton)
  • Duration of each project (5 years for Hazardville, Crandall, Parkman and Barnard; 4 years for Eagle Academy at Eli Whitney). Total overall project duration: 7 years. (provided by Tecton)
  • State reimbursement rate 82.5%, Town Share 17.5% (provided by Tecton)
  • We would issue bonds totalling $89 million to pay for this project
  • Duration of each bond issue: 20 years
  • Bonds will be issued at various points throughout the project. Total duration of bond payments will be 29 years.
  • Bond issue interest rate: 5.25%; Bond Anticipation Note interest rate: 3%
  • Actual rates will be subject to market conditions at the time of issue
  • Value of 1 mill ($3,603,637) based on FY27 budget will not change

Explanation of Results:

The column labeled Estimated Annual Tax Impact shows the estimated annual increase to your taxes caused by the PreK to 5 + Eagle Academy project.

For your individual scenario, you would add that dollar amount to your current annual property tax bill.

The additional rows show the future tax increases, with additional bonds issued, based only on the July 2026 to June 2027 fiscal year and the appraised value from the October 1, 2025 Grand List.

Estimates do not take into account future increases in the Town budget, including operating costs and capital projects; available exemptions or tax abatements; or future revaluations. Actual tax impacts may vary.

The total at the bottom adds together the annual estimates displayed for fiscal years 2029 through 2057. It is a cumulative illustration based on the same entered property value, not a prediction of the exact amount a taxpayer will pay over the life of the borrowing.